Many people think a pergola is just a shade structure: order it, get it delivered, put it up. With a small standard pergola that is how it goes. A non-standard one is a different story: it has to be calculated, drawn and signed off by an engineer. Then it stands for years and you have no trouble with the municipality.

When a pergola needs a special calculation
You need one if you want any of these:
- A bigger pergola. The bigger the pergola, the longer the spans and the greater the load on beams and columns. If you want a large pergola, it has to be calculated and signed off. Pergolas over 50 m² also need a building permit.
- Something heavy on top. Anything you plan to put on the pergola roof adds weight. It has to be included in the calculation in advance, not after installation.
- Upper floors. The wind is stronger at height, so the load on the structure is greater than in a yard at ground level.

What you end up with
A structural engineer prepares a design: materials, profile sections, connections and foundations. Every joint is detailed in the drawing down to the bolts. We order the metal from that drawing and assemble the pergola without changing anything on site.

The sequence of work
Pergola under 50 m²
- Engineer's design. We commission a custom design from a structural engineer. He specifies all the materials and checks that the structure will carry the loads.
- Materials and delivery. Once the specification is ready, we order aluminum from the supplier following the engineer's instructions. The materials are delivered straight to your property. Unloading is included in the price.
- Installation. We assemble the pergola to the engineer's design. The columns stand on concrete plinths. The installation itself takes a couple of days.
- Inspection. The engineer comes, inspects the finished structure and signs off.
- Approval. Approval is done online: you send the engineer's documents to the municipality.

Pergola of 50 m² and over
If the pergola is 50 m² or more, a building permit is required. The route is longer:
- We submit an inquiry to the municipality to find out which permit is needed. The answer can take up to 45 days, sometimes less.
- We obtain the permit itself. This can take up to three months.
- Once the permit is issued, we prepare the documents, build the pergola and complete the final approval for use.
What we do and what is left for you
We walk the whole design and approval route for you. We order the design from the engineer, deal with the permits, prepare the documents, build, and wait for the engineer's sign-off after installation.
All that is left for you is to send the finished documents to the municipality online.
On timing
On the short route the installation itself takes a couple of days and all the administrative part about a week. The long route is counted in months. If you want to finish by a certain date, find that out before the installation date is set.
Need a bigger or non-standard pergola?
Write to us on WhatsApp and send the yard dimensions and a photo. You do not need to understand drawings and codes: we go through this with the engineer, and you only send the documents.